TKT-2026-0112in progresshighescalation
Railing installation delayed by a week
Fabrication was completed on time but installation has not started. No update from the vendor for four days.
Priya Sharma · client · 19 Aug, 10:00 am
Neha (Aangan support):We have spoken to the fabricator. Installation is scheduled for this Saturday and we will confirm the slot with you by Thursday.29 Aug, 10:00 am
TKT-2026-0121resolvedmediumquery
Can the painting quotes include the damp treatment?
Two of the painters mentioned damp behind the kitchen but only one priced the treatment. Can all three quote it the same way so I can compare properly?
Priya Sharma · client · 27 Aug, 10:00 am
Kavita (Aangan support):Good catch — we have asked all three to price the damp treatment as a separate line item so the base painting figure stays comparable between them. Revised quotes are due by tomorrow evening.28 Aug, 10:00 am
Priya Sharma:Perfect, thank you. That is exactly what I needed.28 Aug, 10:00 am
TKT-2026-0119openlowquery
How do I add Painting to my profile?
I also take painting work. How can I start receiving painting leads?
Mohd Arif · professional · 26 Aug, 10:00 am